Short Term Goals to Ensure the Success of the Tahoe Integrated Information Management System (TIIMS)

TIIMS is a comprehensive information management system developed to support environmental restoration and planning activities in the Lake TahoeBasin.  Much work has been done to ensure that TIIMS is a valuable resource for Basin stakeholders.  An extensive Requirements Analysis was conducted at the onset of the project to identify information resources, information needs, information management systems, and the desired functionality of TIIMS.  In January 2004, the TIIMS prototype, which incorporates the highest priority functions, was released.

One of the most important benefits of TIIMS is how it facilitates collaboration and coordination of the many federal, state, and local agencies involved in restoration efforts in the Basin.  This makes TIIMS a valuable tool for agencies that use the system.  But, the continued development and success of TIIMS depends on the continued support and participation of the Partner Agencies.  For TIIMS to move forward in a timely and efficient manner into the production phase (i.e., full development), several key steps need to happen.  These steps relate to (1) management needs, (2) systems support and development, and (3) development of system standards and protocols.  A commitment of both financial resources and management and personnel support from participating agencies is needed to ensure that these steps happen.  A description of these steps and the estimated costs are provided below.  For ease of calculation, it is assumed that each hour of labor, fully loaded, would cost approximately $100, and that there are 2,080 working hours in a year; costs are rounded up to the nearest $1,000.  Therefore, the estimated costs below are an approximation.

 

1.0       Management Needs

Developing a TIIMS administrative framework is critical to the future success of TIIMS.  The existing Project Team provides a good foundation for this structure and has been integral to the development of the prototype.  However, as the system moves into full production, the time required to participate and oversee the development of the system will increase.  It is anticipated that the following commitment of agency personnel will be needed in the next year to keep TIIMS moving forward in a timely manner.

 

2.0       System Support and Development

The prototype incorporates many high priority functions including the ability to search, discover, and access metadata and data, as well as interactive mapping capabilities including the ability to access real-time and historical data.  The following specific tasks conducted in the near future will help TIIMS move into the Production Phase.  

3.0       Development of System Standards and Protocols

To ensure that high quality data and information are posted on TIIMS, data standards and protocols need to be developed and implemented.  Development of these standards will be overseen by the relevant Work Group, with support from technical staff as needed.  Currently, three distinct tasks are the highest priority:

 

Management Needs for First Year

Costs (thousands of dollars)

Percent of Total

 

TIIMS Coordinator

$208

 
 

Project Team Involvement (assumes 15 members)

$288

 
 

Work Group (assumes 10 active members)

$288

 
 

Total Management Costs

$784

37%

System Support & Development

   
 

Information Needs - Coordinator (1.5 years)

$312

 
 

Information Needs - Agency Contribution (assumes 6 agencies)

$89

 
 

Conduct Public Outreach

$150

 
 

Revise Protoype & Integrate Search Engines

$260

 
 

Enhance Workspace Portal

$100

 
 

Develop & Post Electronic Materials

$18

 
 

Edit Prototype Content

$52

 
 

Technical Support to Develop Nodes

$72

 
 

Total System Support and Development Costs

$1,053

50%

Development of System Standards and Protocols

   
 

Monitoring Protocols & Standards - Coordinator

$104

 
 

Monitoring Protocols & Standards - Work Group Participation (assumes 10 active Work Group Members)

$96

 
 

Geographic Reporting Standards - Coordinator

$18

 
 

Geographic Reporting Standards - Work Group Participation (assumes 10 active members)

$20

 
 

Develop & Post TIIMS Guidance Manual

$35

 
 

Total Development of System Standards and Protocol Costs

$273

13%

Total Costs to Move Into Production Phase

$2,110

100%

       
 

  Costs to Move TIIMS to Production Phase